Wastewater treatment plant Magdalensberg

Wastewater treatment plant Magdalensberg

In 2002, the planning, construction and operation of the sewage system Magdalensberg was commissioned.

The sewer system Magdalensberg was put into operation in 2003. The central operations management of EVN Abfallverwertung NÖ takes care of purchasing, operational processes, and any other aspects of technical and commercial operations management. The personnel is in charge of the elaborate inspection and maintenance work.


 

Technical specifications

Operations model sewer system
  Figure Unit
Sewer 55 km
Total investments 9,5m
Construction time 3 years
First operation 2003 2003 -