Zellerbecken

Zellerbecken

In 2002 the expansion and modernisation of the wastewater Treatment plant Zellerbecken was completed, and EVN Abfallverwertung NÖ commissioned to operate it for a period of 25 years.

The central operations management of EVN Abfallverwertung NÖ takes care of purchasing, operational processes, and any other aspects of technical and commercial operations management. The two sewage plant operators receive support in case of elaborate inspection and maintenance work.

 

Technical specifications

 
Operations model wastewater treatment plant
  Zahl Einheit
Wastewater treatment plant capacity 70.000 EW
Total investments 7m
Construction time 24 months
First operation 2002 2002 -
Special plant components
Separate aerobic stabilisation, activation basin with lamella separator